NOνA Change Requests

CR Number CR Title link to docdb. Status (4/15/08)
1 Near Detector Prototype ASIC 2971 Approved
2 IPND ASIC Production 2972 Approved
3 ASIC Prototype II 2973 Approved
4 IPND FEB Production 2974 Approved
5 Extension of I-DEAS CAD Model Engineer thru FY08 for FD Ass'y Integration 2975 Disapproved
6 Extension of FEA Engineer Effort thru FY08 for Far Detector Structural Analysis 2976 Disapproved
7 Produce Electronics Box 2977 Approved
8 Housing Manufacture - Prototype Mold Simplification, Testing Design 2978 Approved
9 OP Errata - WBS 2.5.1.1.6 - matching RLS to BOE for PVC Module End Seal Fiber Manifold Production 2979 Approved
10 OP Errata - WBS 2.0.1.1.2.7, 2.0.1.1.2.9 - matching RLS to BOE for 53 MHz RF System Procurements 2980 Approved
11 OP Errata - WBS 1.5.7.3.5 - matching RLS to BOE for IPND End Plate Components 2981 Approved
12 OP Errata - WBS 2.7.4.1.2.1 - matching RLS to BOE for Detector Controls Systems Procurement 2982 Approved
13 OP Errata - WBS 2.6.1.2.3.39 - matching RLS to BOE for APD Near Detector Manufacturing 2983 Approved
14 OP Errata - WBS 2.10 - Add Admin Asst 2984 Approved
15 OP Errata - WBS 2.2.5.3.1 thru 2.2.5.3.33 - matching RLS to BOE for Far Detector Scintillator Transport 2985 Approved
16 OP errata - WBS 1.3.5.1, 1.3.5.2, 1.3.5.3 - matching RLS to BOE for IPND Fiber Production 2986 Approved
17 OP Errata - Class 2 - 43 small changes correcting discrepancies btwn RLS and BOEs 2966 Approved
18 OP  Errata - Class 3 - 25 small changes correcting discrepancies between RLS and BOEs 2970 Approved
19 Move FY08 Travel From Constn to R&D for WBS x.2 2987 Disapproved
20 Move Production Blending Development from Production to R&D 2995 Approved
21 Production Blending Development FY09, FY10 Labor Increase 2990 Approved
22 Correction to T&M Labor Rates in Open Plan RBS File 2988 Approved
23 Revised Relationships for WBS 2.9 related to CD3a & CD3b 2989 Approved
24 FY08 Subproject Management Task Changes 3030 Approved
25 ANU Task Splits due to Funding Shift 3087 Submitted
26 Removing Gap Clearing Kicker R&D from NOVA Project 3088 In Process
27 Move FY08 Management Labor from R&D to MIE 3075 In Process
28 Splitting of in-progress activities for WBS 1.2 and 1.3 3089 Submitted
29 Splitting of in-progress activities for WBS 1.4 3090 Submitted
30 Splitting of in-progress activities for WBS 1.5 3091 Submitted
31 Splitting of in-progress activities for WBS 1.6, 1.7 3092 Submitted
32 Splitting of in-progress activities for WBS 1.8 3093 Submitted
33 WLS Fiber Procurement FY Budget Adjustments 3094 Submitted
34 Project Management Task Adjustments 3095 Submitted