| CR Number | CR Title | link to docdb. | Status (4/15/08) |
| 1 | Near Detector Prototype ASIC | 2971 | Approved |
| 2 | IPND ASIC Production | 2972 | Approved |
| 3 | ASIC Prototype II | 2973 | Approved |
| 4 | IPND FEB Production | 2974 | Approved |
| 5 | Extension of I-DEAS CAD Model Engineer thru FY08 for FD Ass'y Integration | 2975 | Disapproved |
| 6 | Extension of FEA Engineer Effort thru FY08 for Far Detector Structural Analysis | 2976 | Disapproved |
| 7 | Produce Electronics Box | 2977 | Approved |
| 8 | Housing Manufacture - Prototype Mold Simplification, Testing Design | 2978 | Approved |
| 9 | OP Errata - WBS 2.5.1.1.6 - matching RLS to BOE for PVC Module End Seal Fiber Manifold Production | 2979 | Approved |
| 10 | OP Errata - WBS 2.0.1.1.2.7, 2.0.1.1.2.9 - matching RLS to BOE for 53 MHz RF System Procurements | 2980 | Approved |
| 11 | OP Errata - WBS 1.5.7.3.5 - matching RLS to BOE for IPND End Plate Components | 2981 | Approved |
| 12 | OP Errata - WBS 2.7.4.1.2.1 - matching RLS to BOE for Detector Controls Systems Procurement | 2982 | Approved |
| 13 | OP Errata - WBS 2.6.1.2.3.39 - matching RLS to BOE for APD Near Detector Manufacturing | 2983 | Approved |
| 14 | OP Errata - WBS 2.10 - Add Admin Asst | 2984 | Approved |
| 15 | OP Errata - WBS 2.2.5.3.1 thru 2.2.5.3.33 - matching RLS to BOE for Far Detector Scintillator Transport | 2985 | Approved |
| 16 | OP errata - WBS 1.3.5.1, 1.3.5.2, 1.3.5.3 - matching RLS to BOE for IPND Fiber Production | 2986 | Approved |
| 17 | OP Errata - Class 2 - 43 small changes correcting discrepancies btwn RLS and BOEs | 2966 | Approved |
| 18 | OP Errata - Class 3 - 25 small changes correcting discrepancies between RLS and BOEs | 2970 | Approved |
| 19 | Move FY08 Travel From Constn to R&D for WBS x.2 | 2987 | Disapproved |
| 20 | Move Production Blending Development from Production to R&D | 2995 | Approved |
| 21 | Production Blending Development FY09, FY10 Labor Increase | 2990 | Approved |
| 22 | Correction to T&M Labor Rates in Open Plan RBS File | 2988 | Approved |
| 23 | Revised Relationships for WBS 2.9 related to CD3a & CD3b | 2989 | Approved |
| 24 | FY08 Subproject Management Task Changes | 3030 | Approved |
| 25 | ANU Task Splits due to Funding Shift | 3087 | Submitted |
| 26 | Removing Gap Clearing Kicker R&D from NOVA Project | 3088 | In Process |
| 27 | Move FY08 Management Labor from R&D to MIE | 3075 | In Process |
| 28 | Splitting of in-progress activities for WBS 1.2 and 1.3 | 3089 | Submitted |
| 29 | Splitting of in-progress activities for WBS 1.4 | 3090 | Submitted |
| 30 | Splitting of in-progress activities for WBS 1.5 | 3091 | Submitted |
| 31 | Splitting of in-progress activities for WBS 1.6, 1.7 | 3092 | Submitted |
| 32 | Splitting of in-progress activities for WBS 1.8 | 3093 | Submitted |
| 33 | WLS Fiber Procurement FY Budget Adjustments | 3094 | Submitted |
| 34 | Project Management Task Adjustments | 3095 | Submitted |