Director's/DOE's Performance Management System Review of the NOνA Project June 19-20, 2007 (under construction)
Link to the Directorate Web Page for this review
Review Overview Information
Agenda
(with links to talks)
Other Review Documents
Project Management Plan
(PMP)
Project Execution Plan
(PEP)
Aquisition Strategy
Environmental Assessment
(EA), EAW
Quality Assurance (QA) Plan
Risk Management
Integrated Safety Managment Program
(ISM)
Security Vulnerability Assessment
Contingency Rules
Procurement Plan
Configuration Management Plan
Cost and Schedule from the RLS
Budget and Contingency (R & D)
Budget and Contingency (Construction)
Activity Notes (R & D)
Activity Notes (Construction)
Gantt Chart (R & D)
Gantt Chart (Construction)
Reference Material
NOνA's EVMS Description Supplement
NOνA's Compliance to 32 Criteria Spreadsheet
NOνA Documents
Document Database
CDR
Proposal
Reference
P5 report
NuSAG report